High St (North)
The council received National Stronger Regions Funding from the Federal Government to conduct works in the CBA, which will include the completion of works in High St including landscaping. This would be from Bond to South streets.
Works will begin in the northern end of High St and the intersection with South St in January 2018 .
The works will include the reconstruction of High St from Bond St to South St which will upgrade underground services in the area.
The works will also include landscaping, beautification and new street lighting, the undergrounding of overhead cables and reconstruction of Bond St.
Main features
- Reconstruction of High St from Bond St to South St
- Will remove dip in the road and improve drainage in the area
- Angled parking to remain
- Work will include landscaping, beautification, new street lighting
Project Timeline

Tuesday, February 20, 2018
Intersection open
The High and South streets intersection is now open. Thank you for patience.
Works continue to progress well in High St.

Friday, February 2, 2018
Intersection update
The intersection works are progressing well. However, on excavating the traffic signals, it was found that the existing infrastructure was in poor condition and unable to be reused for the new build.
This means all the inground infrastructure for the traffic signals is being replaced, leading to a possible extension of these works of up to two weeks, subject to weather.
Unfortunately, there was no indication of the extent of the issues which only became apparent after excavation commenced.
The overall project timeline remains unchanged.

Thursday, January 25, 2018
Works update
The diggers have made good progress in High St in the first three weeks of this stage of works.
Works will now focus on completing the underground services and preparing the road surface.

Monday, January 15, 2018
Northern end works begin
Works will begin today (Monday, January 15, 2018) in the northern end of High St. The section of High St between South St and Elgin Boulevard will be closed to vehicular traffic. Pedestrian access will remain at all times.
The intersection of High and South streets will be closed for about four weeks, subject to weather, while the intersection is reconstructed.